top of page
Infographics_Flag_Design.png

CR 205 (Seawillow Road) at Sixmile Branch

Commissioner Westmoreland, Precinct 1 & Commissioner Horne, Precinct 2 | Design Engineer: Pape-Dawson Consulting Engineers, LLC

The project will plan, design, and construct new drainage infrastructure and roadway improvements at Sixmile Branch to provide a safe crossing during flooding and high-intensity storm events. The existing low-water crossing includes culverts and one narrow deteriorating travel lane in each direction without shoulders.


IMPROVEMENTS

  • Upgrading the drainage infrastructure

  • Reconstructing and widening the roadway to include:

    • One 12-foot lane in each direction

    • Shoulders and guardrails over the creek


COST: $3.32M


PURPOSE

  • Enhance overall roadway safety

  • Mitigate flooding risks

  • Provide a safer and more reliable creek crossing


RIGHT OF WAY

This project may require additional right of way to complete construction. Once design is underway, a better estimate of right-of-way needs will be determined.


SCHEDULE

DESIGN: 2025 — 2027

CONSTRUCTION: 2028 — 2029

The existing low-water crossing will be evaluated to determine its existing capacity and future needs. Design is expected to be completed by mid-2027, with construction anticipated to begin in early 2028. Construction will be phased over approximately 12 months. All timelines are estimates and will be updated as the project progresses.

Contact

  • Facebook
Sign up for email updates to receive information on project status and major milestones.

© 2025 by Caldwell County Road Bond

Caldwell county Road Bond logo
bottom of page