CR 182 (Dry Creek Road) at Dry Creek

Commissioner Thomas, Precinct 4 | Design Engineer: RS&H, Inc.

The project will plan, design, and construct a new drainage infrastructure and roadway improvements at Dry Creek to provide a safe crossing during flooding and high-intensity storm events. The existing low-water crossing includes a single narrow, unpaved, and deteriorating travel lane without shoulders.


IMPROVEMENTS

  • Upgrading the drainage infrastructure

  • Reconstructing and widening the roadway to include:

    • One 12-foot lane in each direction

    • Shoulders and guardrails over the creek


COST: $3.23M


PURPOSE

  • Enhance overall roadway safety

  • Mitigate flooding risks

  • Provide a safer and more reliable creek crossing


RIGHT OF WAY

This project may require additional right of way to complete construction. Once design is underway, a better estimate of right-of-way needs will be determined.


SCHEDULE

DESIGN: 2025 — 2026

ROW & UTILITIES: 2026 — 2027

CONSTRUCTION: 2027 — 2028

The existing low-water crossing will be evaluated to determine its capacity and future needs. Design is expected to be completed by mid-2026, with construction anticipated to begin in early 2027. Construction will be phased over approximately 12 months. All timelines are estimates and will be updated as the project progresses.