CR 133 (Ivy Switch) at McNeil Creek

Commissioner Horne, Precinct 2 | Design Engineer: Halff Associates, Inc.

This project will plan, design, and construct new drainage infrastructure and roadway improvements at McNeil Creek to provide a safe crossing during flooding and high-intensity storm events. The existing low-water crossing includes one narrow and deteriorating travel lane in each direction without shoulders or bridge rails over the creek.


IMPROVEMENTS

  • Upgrading the drainage infrastructure

  • Reconstructing and widening the roadway to include:

    • One 12-foot lane in each direction

    • Shoulders and bridge rails over the creek


COST: $3.23M


PURPOSE

  • Mitigate flooding risks

  • Provide a safer and more reliable creek crossing

  • Enhance overall roadway safety


RIGHT OF WAY

This project may require additional right-of-way to complete construction. Once design is underway, a better estimate of right-of-way needs will be determined.


SCHEDULE

DESIGN: 2025 — 2027

CONSTRUCTION: 2028 — 2029

The existing low-water crossingwill be evaluated to determine itsexisting capacity and future needs. Design is expected to be completed by mid-2027, with construction anticipated to begin in early 2028. Construction will be phased over approximately 12 months. All timelines are estimates and will be updated as the project progresses.