top of page

CR 179 (Sendero Homannville)
Comisionado Thomas, Distrito 4 | Ingeniero: RS&H, Inc.


This project will design and construct repairs to CR 179 (Hommanville Trail), including roadway resurfacing, beginning at FM 1185 and continuing northwest along 1.56 miles of CR 279.
IMPROVEMENTS
Repaving and repairing the roadway
COST: $1.2M
PURPOSE
Address deteriorating pavement
Enhance overall roadway safety
Improve mobility
RIGHT OF WAY
This project is not anticipated torequire additional right of way to complete construction.
SCHEDULE
DESIGN: 2025 — 2026
CONSTRUCTION: 2026
Design is expected to be completed by early 2026, with construction anticipated to begin in mid-2026. All timelines are estimates and will be updated as the project progresses.
Contacto
Teléfono: (512) 813-1835
Correo electrónico: info@caldwellroadbond.com
Regístrese para recibir actualizaciones por correo electrónico para recibir información sobre el estado del proyecto y los principales hitos.
bottom of page