CR 179 (Barth Road)
Comisionado Thomas, Distrito 4 | Ingeniero: RS&H, Inc.


This project will design and construct repairs to CR 179 (Barth Road), including roadway resurfacing, to improve pavement conditions from FM 1185 to Morning Mist.
IMPROVEMENTS
Repaving and repairing the roadway
COST: $595,000
PURPOSE
Repair deteriorating pavement
Enhance overall roadway safety
Improve mobility
RIGHT OF WAY
This project is not anticipated to require additional right of way to complete construction.
SCHEDULE
DESIGN: 2025 — 2026
CONSTRUCTION: 2026
Design is expected to be completed by early 2026, with construction anticipated to begin in mid-2026. All timelines are estimates and will be updated as more info becomes available.